Hidden stormwater problems push up costs. Will South Whitehall's Jordan Creek trail link to Parkland High stay on track?

South Whitehall advanced design and permitting for the Jordan Creek Greenway extension as stormwater requirements raised engineering costs.

3D editorial caricature of fictional planners examining a greenway map beside a creek drainage culvert and farm
Editorial illustration
See the story visuallyThree quick views of this story

Visual summary

01 / At a glance

The main point

South Whitehall advanced design and permitting for the Jordan Creek Greenway extension as stormwater requirements raised engineering costs.

02 / By the numbers

The number

5-0

South Whitehall commissioners voted 5-0 to keep work going on the next part of the Jordan Creek Greenway trail.

03 / Still unknown

What we don't know

The source did not say how much higher the building costs could go, whether the $2.1 million estimate includes the new stormwater work, or whether the three property owners have agreed to the trail.

Want the full context? Read the article ↓

South Whitehall commissioners voted 5-0 to keep work going on the next part of the Jordan Creek Greenway trail.

The vote came at the Oct. 21 meeting. It lets the township spend money on design, engineering and permits for trail segments 35 through 40.

That part of the trail would run from Parkland High School toward Covered Bridge Park.

Chris Strohler is the township's long-range planner. He said the township has won about $2 million in state grants. The project is expected to cost about $2.1 million.

The grants include $1.5 million from a PennDOT grant program. It is called the Transportation Alternatives Set-Aside Program. The township also got a new $500,000 grant for engineering and building, Strohler said.

Commissioners agreed to spend up to $100,000 from this year's A capital budget is money set aside for big projects.

That money includes a $64,974 deal with Michael Baker International, an engineering company.

The board also approved a second deal for $81,938 in 2027. That deal only goes through if the township passes its 2027 budget.

Strohler said the trail was first planned in two parts.

The first part, segments 41 through 45, runs inside Covered Bridge Park. It was finished in 2024 with about $1 million from PennDOT, he said.

The second part will cross three privately owned properties between the park and the high school.

Strohler said surprise rules have made the work harder. Stormwater is rain that runs off the land.

Commissioner Sharon Fehringer-Ricker asked if those problems would change the trail's design and cost.

Strohler said rainwater runs through ravines on nearby land. That means engineers must build bigger drains than first planned.

One piece of the trail will cross a working farm. It needs a structure that can handle water and hold the weight of farm machines, Strohler said.

Chris Stanford is a project manager with Michael Baker International. He said the permits and stormwater rules are much harder this time than in the first part.

Stanford said that means more engineering work and higher building costs.

The township plans to keep up engineering work through the winter, Strohler said. It will seek PennDOT approval in spring 2027.

The project could go out for bids in late 2027 or early 2028, he said.

Board President Jacob Roth thanked Strohler and the engineering company. He also praised Strohler for writing the grant requests that brought in the money.