Planners call a 2.1-gigawatt data center plan in Upper Mount Bethel an "infrastructure problem of biblical proportions"
Regional planners requested more detail on two alternative designs for an Upper Mount Bethel data center campus.

See the story visuallyQuick views of this story
Visual summary
Two alternatives
The submitted plans show either 29 buildings or six buildings; the designs are alternatives, not additive.
2.1 gigawatts
Both designs list a power need of 2.1 gigawatts.
Township decision
The outcome of Wednesday’s planning meeting and the supervisors’ vote date were not reported.
Want the full context? Read the article ↓
UPPER MOUNT BETHEL TOWNSHIP, Pa. (Nov. 18, 2026) — Regional planners say two designs for a huge data center campus in Upper Mount Bethel Township leave big questions about power and land. They want more details.
The Lehigh Valley Planning Commission talked about the plans Tuesday. Commissioner Chris Amato led the talk. Getting that much power and water is an "infrastructure problem of biblical proportions," he said, The Morning Call reported.
Slate Belt Holdings sent in both designs. It is a partnership of River Pointe Logistics and Talen Energy. The plans cover more than 900 acres on both sides of River Road.
One design has 29 data center buildings. They total 3.5 million square feet. The other has six buildings. They total nearly 1.5 million square feet. Both list the same power need, 2.1 gigawatts. That left planners unsure about the size of the project.
A spokesperson for the builders told The Morning Call the plans are two ways to use the site. Each would be built in phases. The plans are not meant to be added together, the spokesperson said.
Planners also raised a worry. FirstEnergy has only promised about half the power the project calls for, The Morning Call reported.
In a statement, Slate Belt Holdings said the campus would be built in phases. It said new power sources could come online as it grows. It said the builders, not home or business customers, would pay for any power system upgrades.
Amato said more power means more water. He asked where the water for making that power will come from. The plans call for a link to Portland's public water and sewer systems. Amato said that raises questions about how much they can handle.
The planners' review asks for more details. It asks about upgrades to the power system. It asks for a new study of harm to nature. It asks for pictures of how tall the buildings would look. It also asks about trail links, traffic and noise. And it asks for plans to handle fire risks from battery storage on the site.
Commissioners also said the final review will note that the site matters to the Lenape Nation. Chief Adam Waterbear said the project could cause "severe cultural impact in this area for our people."
WFMZ reported that the township's planning commission was to meet Wednesday at 7 p.m. at the Mount Bethel Firehouse. Township supervisors will make the final call.
Reader poll, not scientific
Do you support a data center campus in Upper Mount Bethel Township?
Your reaction
Want more Lehigh Valley news in your Google results? Add Yooumad as a preferred source.



What do you think?
Join the conversation. A nickname is optional; comments are reviewed for spam and safety.